They managed to alter the plan to ensure the bridge could remain open during the day. There were a series of night time closures instead which took place last year.
The Bridge was going to be closed to carry out work on the High Level Walkways and some parts of the Bascules, after discussion with CoL, TfL and PLA, an alternative method of work was proposed and accepted which resulted in just 28 night-time closures.
I'm pleased that some of you didn't even notice !
The re-painting work is on programme and we will be out of everyones way by the end of March.
Thanks for everyones patience whilst the work has been going on.